Water Connection formalities of Water Meter Division.
1. Scrutinize the status of applications, regarding completion of formal
procedure and issue of demand notices accordingly.
2. Receipt of water connection fee from the consumers as per demand notice.
3. Execution of formal water supply agreement in between the property owner
and the Authority.
4. Documents required for water supply agreement.
5. Issue of material for water connection like clamp, bend tee, pipe, gate
valve, etc. and its endorsement on stock register.
6. Endorsement in ledger register to award ledger number.
7. Physical provision of water connection on ground.
8. Forwarding the water supply agreement documents to revenue documents CDA
for water billing etc.