CAPITAL
DEVELOPMENT AUTHORITY
Islamabad Building Regulations, 1963
NOTICE OF COMPLETION
FORM B-1
SCHEDULE No.1
Islamabad _______
(Date of Delivery at
Authority's Office)
To,
The Capital Development Authority,
Islamabad.
Dear Sir,
I hereby give noticfe of completion of building/additions and/or alternations in the building on Plot No...................... Street No....................... Sector ............................... Islamabad and of drainage and water supply arrangements therein, and apply for your permission to occupy the said building.
2.
The said work has been carried out in accordance with the Building Plans approved
under your No.
3. No Demand Certificates from the Director
Municipal Administration regarding payment of water consumption and Conservancy
Charges are enclosed in original.
4. Cash Receipt in original issued by the Deputy
Director Maintenance regarding re-filling of road cut, sewerage and drainage
is also attached.
(Delete whatever is inapplicable) Yours faithfully,
...............................................
Owner
Name ......................................................
Address ..............................................................................
Dated....................................2010